In this scheme, overall prospect chance has only prospect specific items.
Prospect Chance is divided into five categories: reservoir, seal, structure, charge and recovery
Each category has two or more key elements. You are required to assign a chance to each element. This is a multiplicative scheme and the final category chance is the multiplication of all the element chances.
Individual chances are rounded to the nearest 5%.
The overall Prospect Chance is the multiplication of the prospect specific risk elements:
Overall Prospect Chance = P100 = P(reservoir) x P(seal) x P(structure) x P(charge) x P(recovery)
To each risk category you can also assign a confidence, based on your level of knowledge and supporting data. The confidence can be plotted against chance in a plot: